The Client

A London-based professional services firm with 60 staff across two floors of a Holborn office building. They were relocating to larger premises approximately two miles away in the City of London. Lease end on the existing building was firm — there was no flexibility on timing.

The firm's IT environment included approximately 65 workstations, 6 server racks, a structured cabling installation, 8 meeting rooms each with AV and video conferencing equipment, a reception area with display screens and a VOIP phone system serving 60 extensions.

The Challenge

The relocation needed to be completed between close of business on Friday and start of business Monday — a 60-hour window. The new office had been fitted with basic electrical and data cabling, but no IT infrastructure had been installed. Every element of the existing IT environment needed to be carefully decommissioned, transported, and reinstalled from scratch at the new site.

The client's IT manager was responsible for server configuration and cloud connectivity. Complianta was engaged to handle all physical IT infrastructure — disconnection, packing, transport, installation and testing.

Pre-Move Planning (Two Weeks Before)

Two weeks before move day, Complianta's project lead visited both sites. At the existing office, we conducted a full IT asset audit — every workstation, peripheral, server, switch, access point, cable run and AV unit was catalogued. Each item was photographed in situ and assigned a destination location at the new site.

At the new site, we reviewed the existing infrastructure and produced a rack layout, desk allocation plan and network cabinet design. Any gaps — additional patch cables, new rack units, cable management equipment — were ordered and delivered ahead of move day.

Why planning matters more than speed

The most common cause of a weekend office move overrunning is a lack of preparation. When our team arrives on site, every item should already be labelled, every destination already mapped, and every piece of equipment needed at the new site already there. Speed on move day comes from thorough preparation, not rushing.

Friday Evening: Decommissioning the Old Site

Our team of eight engineers arrived at 6pm Friday. We worked methodically through the office floor by floor:

By 11pm Friday, the old office was fully decommissioned and all equipment was staged in the ground floor reception, ready for the removal company's arrival at midnight.

Saturday: Transport and New Site Setup

The removal company transported equipment across London overnight. Complianta's team was at the new site from 7am Saturday. As equipment arrived, our engineers began installation in parallel across the two floors:

Sunday: Testing, Snagging and Sign-Off

By Sunday afternoon, all physical installation was complete. We spent Sunday evening working through a full testing checklist:

  1. Every workstation powered on and confirmed connecting to the network
  2. Every meeting room AV system tested — display, conferencing camera and presentation switching
  3. VOIP system tested — internal calls, external calls and voicemail
  4. Printer and MFD registration confirmed on the network
  5. Wi-Fi coverage walked and verified across both floors
  6. All snagging items identified and resolved

The client's IT manager confirmed all systems operational at 9pm Sunday. The business was fully operational when staff arrived Monday morning.

What Was Left at the Old Site

A small number of items — ageing workstations and peripherals that the client chose not to relocate — were left for certified disposal. Complianta collected these items during the Friday decommission and processed them through our IT disposal service, issuing Data Destruction Certificates for all devices containing storage media.

Lessons and Principles for Any Office IT Move

Planning an Office Move?

The earlier Complianta is involved, the smoother your move will be. Get in touch to discuss your relocation — no obligation.